How do 3yr infrastructure costs for VMware compare between the following?:
  • On-premises infrastructure 
  • Hybrid Cloud with 50% of VMs using on-premise and 50% of VMs using Public Cloud
  • Public Cloud VMware Cloud (VMC) on AWS - 3 year subscription
Lets say we need 1000 VMs with the average VM being:
  • 2 vCPUs
  • 8 GB  memory
  • 200 GB storage @ 300 IOPS
Hence we need:
  • 2000 vCPUs
  • 8 TB memory
  • 200 TB @ 300,000 IOPS

In the model  I have two different scenarios:

  • Greenfields, completely new site for 1000 VMs
  • Additional 100 VMs
All On-Prem InfrastructureHybrid 50% On-Prem Hybrid 50% Public CloudTotal HybridAll Public Cloud
Greenfields 1000 VMs VMC - $1,725,000VMC - $1,725,000VMC - $2,600,000
Facilities (assume on-prem only 4 racks!!!)$360,000$270,000Included in VMC service$270,000Included in VMC service
Network (assume on-prem only $200K)$200,000$150,000Included in VMC service$150,000Included in VMC service
Firewall (assume on-prem only $200K)$200,000$150,000Included in VMC service$150,000Included in VMC service
Load Balancers (assume on-prem only $200K)$200,000$150,000Included in VMC service$150,000Included in VMC service
Compute$400,000$250,000Included in VMC service$250,000Included in VMC service
Storage$250,000$150,000Included in VMC service$150,000Included in VMC service
SAN (assume on-prem only $100K)$100,000$75,000Included in VMC service$75,000Included in VMC service
vSphere Licences and 3yr support $180,000$90,000Included in VMC service$90,000Included in VMC service
Backup$280,000$140,000$375,000$515,000$750,000
Staff Costs (assume 5 staff to support facilities, compute, storage, SAN, backup, vSphere, network, firewalls, load balancers)$1,500,000$1,200,000Included in VMC service$1,200,000Included in VMC service
TOTAL 3 year cost$3,670,000$2,625,000$2,100,000$4,725,000$3,350,000
Cost per VM/month (3yr commitment)$102$131$93
Additional 100 VMs VMC - $172,000VMC - $172,000VMC - $344,000
Facilities No additional costNo additional costIncluded in VMC serviceNo additional costIncluded in VMC service
Network No additional costNo additional costIncluded in VMC serviceNo additional costIncluded in VMC service
Firewall No additional costNo additional costIncluded in VMC serviceNo additional costIncluded in VMC service
Load BalancersNo additional costNo additional costIncluded in VMC serviceNo additional costIncluded in VMC service
Compute$50,000$25,000Included in VMC service$25,000Included in VMC service
Storage$50,000$30,000Included in VMC service$30,000Included in VMC service
SAN No additional costNo additional costIncluded in VMC serviceNo additional costIncluded in VMC service
vSphere Licences and 3yr support $40,000$20,000Included in VMC service$20,000Included in VMC service
Backup$30,000$15,000$38,000$53,000$75,000
Staff Costs No additional costNo additional costIncluded in VMC serviceNo additional costIncluded in VMC service
TOTAL 3 year cost$170,000$90,000$210,000$300,000$419,000
Cost per VM/month (3yr commitment)$4.72$8.33$11.64

Conclusion from the above model:

  • For 1000 VMs greenfields public cloud is lowest cost as legacy enterprise uses expensive "big brand" products, are inefficient and require vast number of people to support. 
  • For additional 100 VMs  on-premises infrastructure is lowest cost as no additional cost for network, firewalls, load balancers, SAN and staff.
  • Hybrid cloud is expensive as it still requires costs for for network, firewalls, load balancers, SAN and staff. 
  • If possible hybrid cloud should only be an interim step to migrate to public cloud